tfs2017 - Remaining work for bugs not included in work details in TFS 2017.2 -




i have bugs have values in remaining work field want show when column visible , count towards assigned work user in work details section in tfs when looking @ sprint.

i have working bugs setting set bugs managed requirements want bugs appear in backlog along product backlog items , don't want have create task each bug manage remaining time.

i can working if change working bugs setting bugs managed tasks bugs grouped , show unparented , can't order them product backlog items. doesn't work i'm trying achieve.

i want have mix of bugs , product backlog items in sprint assigned multiple users , see how many hours each user has assigned them week can planed out.

is there setting can put against bug work item type make sure remaining work show in work details section , burndown chart?

a bit our setup:

  • we using tfs 2017 update 2 on premise
  • using scrum process template
  • working bugs setting set "bugs managed requirements"

in tfs sprint backlog, doesn't list remaining work value set inside each bug if set “bugs managed requirements”. shows sum of remaining work of tasks under bug in sprint backlog. setting, introduced in document.

but there're other methods try:

  1. you create work item queries remaining work values each bug in sprint. add remaining work field column. enter image description here
  2. you use sprint board, add remaining work field card. enter image description here




wiki

Comments

Popular posts from this blog

Asterisk AGI Python Script to Dialplan does not work -

python - Read npy file directly from S3 StreamingBody -

kotlin - Out-projected type in generic interface prohibits the use of metod with generic parameter -